·         Single right lane closure on the westbound Spur 482 frontage road at the u-turn, continuously from 6 PM on Friday, June 15 to 6 AM on Monday, June 18.

·         Single right lane closure on Northwest Highway/Spur 348 at the Irving Convention Center, Friday, May 25 to Saturday, June 30.

·         Various lane closures at Walnut Hill Lane/Brangus Drive, Tuesday, May 29 to Friday, June 1.

·         Single right (outside) lane closure on northbound Belt Line Road between Valley View Lane and Gateway Drive, closed continuously from May 25 to June 15 (closure may be picked up when crews are not working for a period of time).

·         Single left (inside) or right (outside) lane closure on southbound Belt Line Road between Valley View Lane and Gateway Drive, 9 a.m. to 4 p.m. each day from May 28 to June 1, June 4 to June 8 and June 11 to June 15.

http://www.dart.org/about/expansion/construction.asp?zeon=rss25may12